Refurbished Callan Labs open for Autumn 2022

New look Callan labs
Thursday, September 29, 2022 - 14:45

The newly refurbished labs opened in the Callan building on Monday, 26th of September, 2022. The project converted six existing rooms into 2 new look laboratories.
The conversion will accommodate up to 240 Biology and Chemistry students.

The tender process was completed in April 2022 and works commenced in May this year. The main contract was awarded to Kelbuild. The contract value is €1.3M. The project was designed by our inhouse Campus planning and development office architect, Sean Nolan.

Project Management: Brennan and Associates
Quantity surveyors: Brennan and Associates
Structural Engineer: Bowe Consulting Engineers.
Mechanical and Electrical design: Galileo Energy Services.